Abstract:
Construction industry is categorized as risk rising and full of challenges. Projects
encounter number of risks, which affect the project objectives such as scope, cost,
time and quality. Cost is considered as driving force and major problem among
risks in construction projects. Like many countries, cost overrun is also considered
as significant problem in Pakistan. Hence, this research aims to identify risk factor, which could affect the economically sustainable development of construction
project in Pakistan. In order to meet the objectives, a critical literature review
was carried out to identify the economic risk factors. Delphi technique was used
to identify the significant factors to be included in the research. The Delphi process was concluded in three rounds. Different professionals from the construction
field were requested to participate in the process. Based upon the interactions,
sixty six (66) economic factors were shortlisted, which were further categorized
into seven (07) groups including owner/client, contractor, consultant, political
and government, market, technological limitations, and natural causes. A survey
questionnaire was developed which was used to obtain the feedback from industry
participants. A total of 170 questionnaire were distributed and 101 were received
back. The response rate remained almost 60%. Using SPSS, the reliability of the
data was checked which satisfied the threshold level of significance, confirming the
reliability of data to proceed further with the analysis. In order to observe the
data pattern, normality test was performed which resulted in a non-parametric
pattern. The perception level criteria of the respondents in a non-parametric data
pattern was analyzed using Kruskal Wallis test which remained positive. Economic risk factor matrix was developed for each group level as well as overall basis
for top 34 risk factors identified. Impact was categorized into three zones i.e. low,
moderate, and high on the bases of their criticality. An overall matrix on the basis
of top identified economic risk factors was formulated. Out of thirty four (34), ten
(10) factors were observed in high zone and remaining twenty (24) factors were in
moderate zone. Scatter analysis was also performed for individual group. In case
of owner / client group, the range of likelihood of occurrence and magnitude of
impact was 0.35 to 0.61 and 0.25 to 0.42, respectively. For contractor, it remained 0.45 to 6.5 and 0.25 to 0.40. Whereas in case of consultant, it was 0.40 to 0.60 and
0.25 to 0.35 respectively. For the remaining groups like political and government,
market related, and technological limitations, it was observed as 0.45 to 0.62 and
0.22 to 0.37, 0.42 to 0.55 and 0.22 to 0.35, 0.40 to 0.56 and 0.22 to 0.30, respectively. This study helped in early better understanding and awareness of economic
risk factor. The study has achieved a mile stone in development of economic risk
matrix with risk criticality values which is expected to guide the project stakeholders in conducting economic risk analysis during feasibility study. Based upon
these analysis, proper remedial measures would be possible for incorporation at
planning and strategy level to improve and manage these barriers.